Datang Environmental Thailand PTG Biomass Power Plant EPC Project put into commercial operation

2020-06-16

On May 13, 2020, Thailand PTG 1×24MW biomass power plant, an EPC project of Datang Environmental Industry Group Co., Ltd., successfully connected to the grid for power generation and entered commercial operation, marking the successful completion of the construction of the largest biomass power plant in southern Thailand.

The project is located at the junction of Changwat Pattani in southern Thailand and Malaysia, with unit capacity of 24 MW and invested by Thai PTG Company. The completion of the project will realize the efficient use of rubber waste, palm leaves, palm nut shells and other crop wastes in the surrounding areas, and provide clean electricity to the local area, which is of great significance to the social and economic development of Thailand.

The project started in April 2018. The boiler hydraulic test was successful on November 8, 2019. On March 5, 2020, the steam turbine was turned on once, and on April 20, 2020, it was successfully connected to the grid and ready for commercial power generation. It will generate about 192 GWh of electricity annually, and the power shortage in Changwat Pattani in southern Thailand will be greatly alleviated. In addition, the project has an important role in promoting local economic growth and social development.

The project carefully complies with the power engineering construction standards, strictly implements local laws and regulations, implements project management with high standards and strict requirements, and strives to create a quality project.


Copyright© www.maldonarchive.com All Rights Reserved

Address: 1 Guaningbo St., Xicheng Dist., Beijing 100033

Email: cdt-info@china-cdt.com

CDT WeChat

CDT Micro-blog

Produced By CMS 网站群内容管理系统 publishdate:2024-12-04 17:26:40